Bridge Improvements Project

  • Project typeBridge Structural Repairs
  • Project scheduleSeptember 2024 – December 2024 (Tentative)

In 2020, the City established a recurring bridge inspection, maintenance, and repair program. This program includes ongoing inspections of bridge and culvert structures, recommendations for repairs, and maintenance to meet functional and structural improvements in accordance with industry standards. Based on the findings from a condition assessment completed in 2022, the following seven bridges were prioritized for repairs. The structural repairs are corrective and preventive maintenance measures that will prolong the serviceable life of the structures and improve safety. Typical structural repairs include glulam girder repairs, decking and guardrail repair/replacement, and structural section loss repairs.

  • Wilkie Way Pedestrian Bridge at Adobe Creek (Structure No. 1.32)
  • Bol Park Bike Path Bridge at Matadero Creek (Structure No. 1.06)
  • Bol Park Bike Trail Pedestrian Bridge at Barron Creek (Structure No.1.23)
  • Bryant Street Pedestrian Bridge at Matadero Creek (Structure No. 1.02)
  • Laguna Avenue Bridge at Matadero Creek (Structure No. 1.05)
  • Cerrito Way Box Culvert at Barron Creek (Structure No. 1.22)
  • Bryant Street Bicycle Bridge at Matadero Creek (Structure No. 1.03)

Vicinity-Map.jpg

 

Bol Park Bike Path Bridge at Matadero Creek (Structure No. 1.06)

Work Completed

Bol Park Bike Trail Pedestrian Bridge at Barron Creek (Structure No. 1.23)

Work Completed

  • Replaced deck planks, handrail member, deck brace, safety railing; concrete spall patching; removed abandoned conduit. Bridge Location Map 

Bryant Street Pedestrian Bridge at Matadero Creek (Structure No. 1.02)

Work Completed

Wilkie Way Pedestrian Bridge at Adobe Creek (Structure No. 1.32)

Work Completed

  • Repaired/painted glulam girders, replaced select deck planks, concrete spall patching, erosion repair, installed anti-slip fiberglass deck strips in select areas. Bridge Location Map  

Laguna Avenue Bridge at Matadero Creek (Structure No. 1.05)

Work Completed

  • Replaced timber railing with steel railing, modified existing timber railing, replaced utility support bracket. Bridge Location Map 

Cerrito Way Box Culvert at Barron Creek (Structure No.1.22)

Work Completed

Bryant Street Bicycle Bridge at Matadero Creek (Structure No. 1.03)

Work Planned

Project Schedule (Tentative)

  • Work is anticipated to occur from Monday, December 9 through Friday, December 13 (weather permitting)
  • Work hours: 9am – 5pm (weekdays)

Traffic Impacts

  • Bridge will be closed as needed during construction. Bridge users shall follow signage for the detour through the adjacent pedestrian bridge.