Stage 3 – 2019 to 2020

Status: Completed

Date(s):

  • January 2019: California Avenue Area Parking Garage construction begins
  • Parking garage mat slab foundation is poured late September 2019
  • Parking garage construction is substantially complete November 20, 2020.
  • The California Avenue Area Parking Garage opens to the public on December 8, 2020.