Stage 4 – 2021 to 2025

Status: Uncompleted

Date(s):

  • January 2021: The PSB bids were received.
  • February 2021:  City Council awards the construction contract for the PSB to Swinerton Builders.
  • March 2021: The PSB construction begins. 
  • May 2021: Parking Lot C-6 and Sherman Avenue between Park Boulevard and Birch Street are closed to the public. Map of Available Parking in the Area
  • June 2021: The City hosts a groundbreaking reception to celebrate the construction of the PSB. Livestream of the event
  • December 2021: Completion of mat slab pour at the PSB.
  • April 2023: Solar panel installation begins at 350 Sherman parking garage to serve the PSB.
  • October 2023: Completed solar panel installation at 350 Sherman parking garage. Monopole tower installed. Soil cell installation and other site work begins. Interior painting and ceiling closeup begins.
  • November 2023: Interior drywall completed. Casework installation begins. Curb and gutter work begins around perimeter of site.
  • January 2024: Concrete flatwork begins.
  • March 2024: City fiber internet service installed.
  • June 2024: Furniture installation begins.
  • May 2025: Temporary Certificate of Occupancy – Stock and Training received.