2025

Status: Uncompleted

Date(s):

January - March

The Cooperative Agreement was fully executed in early January 2025. Following this, the project team was established in coordination with Caltrain to begin advancing the project from the conceptual phase to the Preliminary Engineering and Environmental Documentation phase. The team began developing the Project Management Plan (PMP), and a summary of the PMP was presented to the Rail Committee for feedback. A Request for Proposals (RFP) was prepared to procure General Engineering Consultant services to refine the conceptual designs and develop 15% engineering plans.

March - June

Caltrain in partnership with the City prepared a Draft Public Outreach and Engagement Plan to gain input from the public, Rail Committee, City Council, and other stakeholders at key project milestones. The plan is intended to support informed decision-making and the evaluation of well-supported project alternatives. TYLin was selected as the General Engineering Consultant to assist City and Caltrain staff in developing the 15% design plans.

A workshop and open house are being planned for August 21 and 26. Check back here for more details including dates and input needed.