Rail Grade Separation

Rail Grade Web Banner

There are seven streets where pedestrians and vehicles can cross railroad tracks in Palo Alto. While three of these intersections — also known as grade crossings — are above the road and already grade separated, there are four remaining that cross the tracks at the same level, posing traffic and safety issues. The City is pursuing grade separation on three existing at-grade crossings: Churchill Avenue, Meadow Drive, and Charleston Road. This process will inform decisions affecting both community aesthetics and mobility choices for many future generations. Community feedback and collaboration is a vital part of the decision-making process.

Project Updates

In June 2024, the City Council advanced the project alternatives for further review and development into the Preliminary Engineering and Environmental Documentation phase of the project. The City secured $6 million in grant funding from the Federal Railroad Administration and executed a cooperative agreement with Santa Clara Valley Transportation Authority to secure $14 million from Measure B Grade Separation Funding for the Preliminary Engineering and Environmental Documentation Phase. Caltrain will be leading the efforts in this phase with the City participating as the project sponsor.

Current Alternatives

Note: Renderings of each are in the Project Resources below.

Churchill Avenue Crossings

  • Partial Underpass Alternative with bicycle Pedestrian crossing at Seale Avenue (Preferred Alternative)
  • Closure (Backup Alternative)

Meadow Drive & Charleston Crossings

  • Hybrid Alternative (Mixed wall Column design approach)
  • Underpass Alternative

Caltrain Partnership

Caltrain is leading efforts for preliminary engineering design and environmental clearances required for the project. The project will work towards developing plans at an initial 15% design. The development of the design plans will involve efforts to reduce right-of-way impacts, enhance bicycle and pedestrian connectivity, optimize infrastructure improvements for the partial underpass and underpass alternatives at the three crossing locations. Community and stakeholder engagement will be conducted throughout this phase, with the preliminary designs shared for input to support the Rail Committee’s review and the Council’s selection of locally preferred alternatives. The project will then proceed to develop a 35% design for the selected locally preferred alternatives at each of these crossings.

Concurrently, the project will also include developing environmental documentation in compliance with the National Environmental Policy Act (NEPA)’s and California Environmental Quality Act (CEQA)’s environmental review requirements. Additional outreach will be conducted during this stage of environmental documentation to seek appropriate NEPA and CEQA analysis. This work is anticipated to be completed by fall 2027.

Caltrain's Project Page

Project Resources

Project Studies & Reports

Noise & Vibration Study (July 2020)

         
Noise & Vibration Comparative Analysis Report(PDF, 3MB)

Traffic Study

Churchill, Meadow and Charleston Grade Separation Traffic Analysis Report from Hexagon Traffic Consultants, Inc.(PDF, 9MB) (January 16, 2024)

Churchill, Meadow and Charleston Grade Separation Traffic Analysis Report(PDF, 24MB) (Hexagon Traffic Consultants, Inc., August 13, 2020) **A minor correction/clarification was made and the resulting revision was posted on February 3, 2021** 

Charleston Underpass Traffic Animated Video Simulation AM (July 2020)

Charleston Underpass Traffic Animated Video Simulation PM (July 2020)

Geotechnical Study July 2024

Preliminary Geotechnical Study(PDF, 18MB)

Sea Level Rise Study January 2024

Sea Level Rise Assessment(PDF, 86KB)(PDF, 86KB)

Heat Island Effect & Storm Water Run off Analysis January 2024

Heat Island Effect and Storm Water Runoff Analysis(PDF, 552KB)

Shadow Analysis (Updated Annually)

Meadow-Charleston Viaduct – Summer

Meadow-Charleston Viaduct – Winter

XCAP Final Report(PDF, 60MB) - March 2021

Renderings, Plans & Animations

*Alternatives Still Being Considered*

Churchill Alternatives

Churchill Partial Underpass (the preferred alternative as of November 29, 2021)

Churchill Closure with Mitigations (the backup alternative as of November 29, 2021) 

Meadow-Charleston Alternatives

    Meadow-Charleston Hybrid

    Rendering(PDF, 8MB) (Updated May 2024)
    Plan & Profile(PDF, 89MB) (Updated May 2024)
    Animation (video-Older Version, August 2020)

    Meadow-Charleston Underpass

    Rendering(PDF, 50MB) (Updated May 2024)
    Plan & Profile(PDF, 4MB) (Updated May 2024)
    Animation (video-Older Version, August 2020)

    Meadow-Charleston Trench
    **Removed from consideration by City Council in June 2024**

     Rendering(PDF, 44MB) (Updated August 2020)
    Plan & Profile(PDF, 144MB) (Updated August 2020)
    Animation (video-updated August 2020)

      Meadow-Charleston Viaduct –
      **Removed from consideration by City Council on August 23, 2021;  Re-included for review by Rail Committee on June 20, 2023**

      Rendering(PDF, 72MB) (Updated August 2020)
      Plan & Profile(PDF, 206MB) (Updated August 2020)
      Animation (video-Updated August 2020)

      Historic Timeline

      • 2025

        January - March

        The Cooperative Agreement was fully executed in early January 2025. Following this, the project team was established in coordination with Caltrain to begin advancing the project from the conceptual phase to the Preliminary Engineering and Environmental Documentation phase. The team began developing the Project Management Plan (PMP), and a summary of the PMP was presented to the Rail Committee for feedback. A Request for Proposals (RFP) was prepared to procure General Engineering Consultant services to refine the conceptual designs and develop 15% engineering plans.

        March - June

        Caltrain in partnership with the City prepared a Draft Public Outreach and Engagement Plan to gain input from the public, Rail Committee, City Council, and other stakeholders at key project milestones. The plan is intended to support informed decision-making and the evaluation of well-supported project alternatives. TYLin was selected as the General Engineering Consultant to assist City and Caltrain staff in developing the 15% design plans.

        July - November

        In collaboration with City staff, Caltrain refined the conceptual designs for the partial underpass alternative for Churchill Avenue, as well as hybrid and underpass alternatives for the Meadow Drive and Charleston Road grade separation projects. Caltrain also developed initial concepts for Seale Avenue as part of Churchill Avenue grade separation. These revisions respond to City Council direction aimed at minimizing right-of-way impacts and enhancing mobility as part of the Preliminary Engineering and Environmental Documentation phase.

        Staff will present revised conceptual plans to the Rail Committee and community for review and feedback, plus direction on Locally Preferred Alternatives to advance into the 15% design phase.

      • 2022 - 2024

        01/2022 - 12/2024

        Winter 2024

        City staff collaborated with Caltrain and Caltrain and Valley Transportation Authority (VTA) to establish a three party Cooperative Agreement.  This agreement outlines the roles and responsibilities for conducting the Preliminary Engineering and Environmental documentation and includes a $14 million funding contribution from Measure B Grade Separation funds for the Churchill Avenue, Meadow Drive, and Charleston Road crossings.  The funding agreement was authorized by the three parties and fully executed.

        Summer/Fall 2024

        The funding agreement with the FRA for Preliminary Engineering and Environmental Phase was finalized. City staff worked with Caltrain and VTA to develop a three party Cooperative Agreement.  In addition, City and Caltrain staff presented updates on the Enhanced Crossing project near the Churchill Avenue crossing to the Rail Committee.

        Summer 2024

        The Rail Committee continued evaluating project alternatives, focusing on the implications of aligning with Caltrain's comments and standards.  City and Caltrain staff presented findings on necessary modifications to the conceptual designs, seeking input to guide the next phase of development. 
        The committee recommended advancing the underpass and hybrid alternatives for Charleston Road and East Meadow Drive to preliminary engineering, with an emphasis on minimizing property impacts, enhancing bike/pedestrian crossings, and improving connectivity to existing infrastructure.  
        For Churchill Avenue, the committee reaffirmed its commitment to the underpass alternative and designated Seale Avenue as the preferred location for a bike/ pedestrian crossing associated with this alternative.

        In June, following a review of the Rail Committee's recommendations and public feedback, the City Council approved advancing these projects to the Preliminary Engineering and Environmental Phase.  Council also endorsed a funding agreement between the City of Palo Alto and the Federal Railroad Administration (FRA) for $6million in grant funding under the Rail Crossing Elimination Program.

        Spring 2024

        Caltrain staff conducted their initial technical review relative to Caltrain Standards and roadway standards and provided comments to City Staff on the conceptual plan alternatives in November 2023. These comments and concerns were extensively discussed during the January Rail Committee meeting, and staff sought guidance on substantiating changes in the alternative concepts, focusing on major elements such as right-of-way encroachment, vertical alignment, horizontal alignment, and other miscellaneous items.

        Subsequently, City and Caltrain staff convened to comprehend how addressing Caltrain comments and adhering to Caltrain Standards would impact the conceptual design alternatives. The objective was to  understand the high-level material changes that may be required for the concepts and explore next steps.

        Additionally, during the February Rail Committee meeting, staff presented the updated Summary of Evaluation Matrix. This update incorporated additional items approved by the Council into the adopted evaluation criteria, including East-West connectivity, Traffic, Pedestrian/bicycle circulation, Private Property Impacts, Environmental impacts, and Visual impacts.


        Fall/Winter 2023

        The City secured a $6.0 Million grant from the Federal Railroad Administration under the Railroad Crossing Elimination Program.  This funding contributes to the Environmental and Preliminary Engineering phase of the grade separations at Churchill Avenue, Meadow Drive, and Charleston Road crossings.

        Additionally, the City received a $23.79 Million grant from a California State Agency under the Transit and Intercity Rail Capital Program.  This financial support is allocated for the Final Design Phase of the Churchill Avenue Grade Crossing.

        City staff is actively engaged in evaluating grade separation alternatives with the intention of updating the matrix to align with the revised City Council Adopted Criteria.  The Rail Committee reviewed proposed metrics by Caltrain for prioritizing Grade Crossings and providing feedback to Caltrain.

        An update on the Bicycle and Transportation Plan Update project was presented and the Rail Committee provided feedback related to crossings across the Rail Corridor.

        Summer 2023

        Following input from various stakeholders, including Palo Alto Unified School District (PAUSD), Stanford, Pedestrian and Bicycle Advisory Committee (PABAC), and community designers involved in the Underpass Alternatives, the Partial Underpass Alternative for Churchill Avenue, and Meadow Drive and Charleston Road Underpass Alternatives were revised and officially endorsed by the Rail Committee.

        The City Council approved the Services Agreement between the City of Palo Alto and the Peninsula Corridor Joint Powers Board (Caltrain) for the Connecting Palo Alto Grade Separation Project.  This agreement facilitates technical input on conceptual designs.

        The City Council approved the proposed updates to the Grade Separation Evaluation criteria, authorizing the Rail Committee to employ these modifications in assessing alternatives under consideration for grade separation projects.

        The Rail Committee re-included the Viaduct Alternative in ongoing consideration for further study by Caltrain and City staff.

        The Rail Committee also reviewed and accepted the preliminary geotechnical report prepared by the project consultant.

        Spring 2023

        Rail Committee reviewed and recommended Council to update the Grade Separation Evaluation Criteria. The revised criteria now include additional factors such as travel times, traffic impacts, long-term maintenance costs, sustainability, sea level rise, as well as consideration of visual and privacy changes.

        Rail Committee reviewed the Services Agreement between City of Palo Alto and Peninsula Corridor Joint Power Board (Caltrain) for the Connecting Palo Alto, Grade Separation Projects and recommended it to the City Council for approval. The purpose of the Service Agreement is to engage Caltrain in early coordination, provide technical review, offer input and expertise, and contribute to the capital project development process for the selection of Preferred Alternative(s).


        Fall/Winter 2022

        Study Sessions were held to review comments received from various stakeholders to refine conceptual plans for Partial Underpass Alternative at Churchill Avenue and Underpass Alternatives at Meadow and Charleston Road. In addition, Staff initiated discussion with Caltrain for a service agreement to review the conceptual plans.

        Summer 2022

        Staff reached out to various stakeholders including (PABAC) Pedestrian and Bike Advisory Committee, PAUSD (Palo Alto Unified School District), Stanford, CSTSC (City School Transportation Safety Committee), and local design engineers as directed by Council to seek input and feedback for refining underpass alternatives.

        Spring 2022

        Rail committee was reinitiated at the direction of the City Council.  At its first meeting in April, the Rail Committee recommended for the Consultant to perform additional studies that included a preliminary geotechnical investigation and design Refinement of the underpass alternatives. In addition, a second opinion will be sought for cost estimates of trench alternatives.

        Council approved the amendment with the City’s Consultant for additional studies recommended by the Rail Committee that included preliminary geotechnical investigation, design refinement of the underpass alternatives, and a second opinion for cost estimates of trench alternatives.

        Staff submitted grant applications requesting federal funding for grade separation projects at the crossings of Churchill Avenue, Meadow Drive, and Charleston Road from various programs such as INFRA 22 known statutorily as the Nationally Significant Multimodal Freight & Highway Projects, MEGA 22 known statutorily as the National Infrastructure Project Assistance program) and through Metropolitan Transportation Commission under Bipartisan Infrastructure Law (BIL).

      • 2019 - 2021

        Fall 2021

        Conducted detailed review of three alternatives being considered for Churchill Avenue railroad crossing; and provided scope and cost for additional studies that may help in decision making for selection of final/preferred alternative(s) at these crossings. Council eliminated the viaduct option from further consideration at this crossing. In addition, Council selected the Partial Underpass Alternative as preferred option and Closure with Mitigation Alternative as the backup Alternative for Churchill. Conducted detailed review of three alternatives being considered for Churchill; and provided scope and cost for additional studies that may help in decision making for selection final/preferred alternative(s) at these crossings. Council eliminated the viaduct option from further consideration at this crossing. Council also directed to place highest priority in addressing the Charleston/Meadow crossing.

        Summer 2021

        Conducted detailed review of four alternatives being considered for Meadow Drive and Charleston Road railroad crossings and provide scope and cost for additional studies that may help in decision making for selection Final/Preferred Alternative(s) at these crossings. Council eliminated the viaduct option and now only three alternatives (Hybrid, Underpass, and Trench) remain for further consideration for final selection.

        Spring 2021

        The XCAP completed their deliberations after reviewing the rail grade crossing alternatives at the three crossings of Churchill Avenue, Meadow Drive, and Charleston Road. The City Council received the final report prepared by XCAP including their findings and recommendations on these rail grade crossings.

        After receiving the XCAP final report and recommendations, the City Council eliminated the following tunnel alternatives from further consideration:

        • South Palo Alto Tunnel (Passenger and Freight)
        • South Palo Alto Tunnel (With At-Grade Freight)

        A total of four (4) alternatives for Charleston and Meadow and three (3) alternatives for Churchill Avenue remain for further consideration.


        Fall/Winter 2020

        XCAP reviewed the various alternatives under consideration and initiated the deliberation process. They also updated the City council on their timings to deliver their recommendations and final report.

        Summer 2020

        The Virtual Town Hall launched; it was live from August 19th through September 14th.

        XCAP initiated deliberation on Churchill Avenue location.

        Staff presented a report to the City Council and described how the Virtual Town Hall  will provide greater flexibility and extended period for community engagement and feedback within the COVID-19 environment.

        Spring 2020

        XCAP provided an update to City Council on their review of grade separation alternatives.

        XCAP provided an update to City Council. Also, XCAP unanimously voted to eliminate two trench alternatives (with and without freight) from their deliberation process.

        Rail Town Hall meetings discussing the rail grade separation alternatives for greater community engagement and participation.

        City Council discusses new and existing alternatives that were narrowed down to seven alternatives for further evaluations. Also directed staff to include two new ideas presented by community members to the City.


        Winter 2019

        Citywide Community Meeting was held where the City started the first of many community conversations about the alternatives still under consideration. It was a comprehensive sharing of information about all seven (7) of the remaining alternatives.

        At the XCAP meetings, the chairperson and vice chairperson were chosen, guiding principles were adopted, and ground rules were established for how they will function as a group and work towards consensus. They also reviewed materials for community outreach.

        Fall 2019

        XCAP had meetings on September 5 and September 25. They discussed proposed design workshop questions, looked at South Palo Alto animations, and discussed the new organization of the XCAP. Council voted to expand XCAP’s role, and the panel now has a chair and co-chair. XCAP decided to postpone the design workshop to a later date.

        City Council sent a letter to Caltrain regarding the Caltrain Business Plan.

        Summer 2019

        City Council approved a $1.2 Million amendment to the AECOM contract to continue services.

        Staff presented an idea to establish a Rail Blue Ribbon Commission to Council. XCAP had a meeting on August 21. XCAP discussed Measure B and a traffic analysis for Churchill Avenue.

        Spring 2019

        City Council convened as the Committee of the Whole to discuss the grade separation alternatives and directed staff to return to the City Council with a rail work plan and a few other action items.

        Community Advisory Panel (CAP) received the traffic analysis for the Churchill Avenue Closure alternative and reviewed the bike/ped crossing options. CAP also prepared for the community meeting.

        The City hosted a community meeting focused on Churchill Avenue and the Citywide Tunnel alternative.

        City Council approved the rail work plan and provided direction to staff regarding the alternatives analysis, check-in meetings, and the AECOM contract. The approved work plan moved the selection date for the preferred alternatives from April 2019 to October 2019.

        City Council further refined the list of alternatives to remove the Citywide Tunnel alternative and to reaffirm consideration of both options for the South Palo Alto Tunnel alternative.

        City Council continued the discussion from December 2018 to narrow the alternatives. City Council also amended the list of alternatives through the following actions:

        • Separated the Palo Alto Avenue crossing from study and including it in a separate comprehensive Coordinated Area Plan process.
        • Separated the bicycle and pedestrian crossing in the vicinity of Loma Verde Avenue from study and including it in another planning process.
        • Directed staff related to the Citywide Tunnel alternative as well as the South Palo Alto Tunnel ideas.
        • Adopted a modified list of grade separation alternatives:
          • South Palo Alto | Rail Tunnel
          • Churchill Avenue | Full or Partial Closure and add Improvements (CAX)
          • Meadow Drive and Charleston Road | Hybrid (MCL)
          • Meadow Drive and Charleston Road | Rail Trench (MCT)
          • Meadow Drive and Charleston Road | Viaduct (MCV)
          • Citywide Tunnel (WBP)
        • Provided direction to staff regarding funding, mitigations, evaluation criteria, and timeline.
      • 2016 - 2018

        Winter 2018

        The City Council received public comment regarding the alternatives still under consideration. They held off a vote until January 2019.

        City Council Rail Committee recommended staff to further explore the South Palo Alto tunnel alternative with freight separate from passenger rail.

        Community Advisory Panel began a discussion about the Evaluation Matrix as well as the detailed review of the Meadow-Charleston exhibits, renderings, and animations.

        The City of Palo Alto hosted a Community Meeting focused on receiving feedback about the alternatives for Meadow-Charleston.

        City Council Rail Committee further discussed the alternatives under consideration and also recommended that the City Council add a South Palo Alto tunnel with single-track freight rail at-grade. The Committee also accepted a work plan and requested a running list of key issues. The Committee also finalized the letter to Caltrain regarding electrification.

        Community Advisory Panel discussed the work plan, the traffic scope, the alternatives, and the financial information. The panel also heard a presentation regarding separating the Palo Alto Avenue crossing out of study for this and into a Coordinated Area Plan. The CAP recommended a focus on the Meadow-Charleston crossings first then the northern crossings.

        Fall 2018

        City Council Rail Committee discussed the proposed Cooperation Agreement with the Peninsula Corridor Joint Powers Board regarding the Caltrain electrification project. They also reviewed the scope for the traffic study for the Palo Alto Avenue Closure and Churchill Avenue Closure alternatives.

        Community Advisory Panel discussed the scope of the traffic study, received an update on the recent community outreach and the alternatives still under consideration, and began discussing financial considerations for grade separation.

        Summer 2018

        City Council Rail Committee met Eileen Goodwin of Apex Strategies (sub-consultant to AECOM) to discuss the community engagement strategy.

        City Council approved the Community Engagement Plan, including the creation of a Community Advisory Panel (CAP). City Council also amended the list of ideas through the following actions:

        • Eliminate the Churchill Avenue Hybrid (CAH) idea from consideration;
        • Eliminate the Churchill Avenue Reverse Hybrid (CAR) idea from consideration;
        • Break out Churchill Avenue closure option into full closure and partial closure;
        • Remove the language regarding widening Embarcadero Road underpass from the description of the Churchill Avenue crossing closed (CAX) idea;
        • Add to Churchill Avenue crossing closed (CAX) idea, “study additional options for addressing traffic in the Embarcadero Road underpass area including actions to minimize redirected traffic onto residential streets in adjacent neighborhoods and commit to adopting appropriate mitigations to address the impacts; and
        • Direct Staff to analyze and return to Council in August or earlier with a report on the impacts to properties for hybrid options for Charleston Road and Meadow Drive.

        City Council Rail Committee received a presentation about the remaining grade separation ideas under consideration.

        Community Advisory Panel held their first meeting and received orientation information about their role and purpose.

        The City of Palo Alto hosted a Community Meeting to hear feedback from the public about the grade separation ideas still being considered as well as the existing conditions.

        Spring 2018

        The Rail Team, comprised of multiple City departments and the City Manager’s Office, implements a project reset to accelerate the planning, design, and construction of railroad grade separations within Palo Alto. Tentative goals are to narrow the suite of alternatives under consideration in 2018 to get to the locally preferred alternatives by December 2018, completing the environmental analysis in 2019, beginning final design in 2020, and starting construction in 2023.

        The City of Palo Alto hosts the Community Roundtable Discussions to discuss the Trench and Tunnel White Paper with the community and to receive feedback.

        Palo Alto City Council Rail Committee hears a summary  of the Community Roundtable Discussions and also receives a report on the initial screening of the Master List of Ideas for grade separation.

        City Council approves a $1.2 Million contract with AECOM to lead the engineering and engagement process for the City’s grade separation process.

        Palo Alto City Council Rail Committee is introduced to the new AECOM team and continues to discuss the Master List of Ideas for grade separation.

        Palo Alto City Council Rail Committee meeting is canceled.

        The City Council discusses the Master List of Ideas and narrows the alternatives to the following:

        • Churchill Avenue roadway under the railroad
        • CAH – Churchill Avenue roadway under railroad hybrid;
        • CAR – Churchill Avenue roadway over railroad reverse hybrid;
        • CAX – Churchill Avenue crossing closed; improvement options include: widen existing Embarcadero Road undercrossing, add new traffic signals at Embarcadero
        • Road ramps, build bike/pedestrian crossing at Churchill Avenue, and/or build Seale Avenue bike/pedestrian crossing to connect to Peers Park and Stanford Avenue bicycle boulevard;
        • MCL – Meadow Drive and Charleston Road railroad over roadway hybrid and build Loma Verde Avenue bike/pedestrian crossing to connect to Margarita Avenue
        • bicycle boulevard;
        • MCR – Meadow Drive and Charleston Road roadway over railroad reverse hybrid and build Loma Verde Avenue bike/pedestrian crossing to connect to Margarita
        • Avenue bicycle boulevard;
        • MCT – Meadow Drive and Charleston Road roadway over railroad trench or tunnel; Alma Street would not be within trench or tunnel (maintains Alma Street connections to Meadow Drive and Charleston Road) with Alma Street in its existing alignment or a new alignment;
        • MCV – Meadow Drive and Charleston Road railroad over roadway viaduct;
        • PAH – Continue proposed Menlo Park railroad over roadway hybrid and/or viaduct across San Francisquito Creek and Palo Alto Avenue;
        • PCX – Palo Alto Avenue crossing closed; improvement options include: build an Everett Avenue bike/pedestrian undercrossing and widen University Avenue;
        • WBP – City-wide deep-bore railroad under roadway tunnel within Palo Alto city limits with two new underground rail stations with or without freight.

        City Council also directed staff to return with an enhanced community engagement plan and to explore the future of freight and the possibility of 2 percent grade. They also requested staff to engage with lobbyists regarding funding and other matters.


        Fall/Winter 2017

        City of Palo Alto hosts a series of three Community Roundtables to engage the public to help evaluate potential grade separation options at each of Palo Alto’s four Caltrain rail crossings.

        Palo Alto City Council Rail Committee receives a presentation by the City of Menlo Park on their Railroad Grade Separation Project at Ravenswood Avenue, Oak Grove Avenue, and Glenwood Avenue.

        Palo Alto City Council Rail Committee receives a presentation by the City of Burlingame on their Broadway Railroad Grade Separation Project.

        Palo Alto City Council Rail Committee reviews the draft Rail Corridor Circulation Study
        White Paper and the draft Rail Financing White Paper.

        Palo Alto City Council Rail Committee receives a Presentation by the Chief Executive Officer of the Alameda Corridor East Construction Authority on their grade separation trench project.

        City council adopts Connecting Palo Alto Problem Statement, Goals, and Evaluation Criteria.

        City of Palo Alto hosts a Connecting Palo Alto: Community Workshop #2 to review Connecting Palo Alto’s problem statement, goals and evaluation criteria, and start discussing design alternatives and constraints for grade crossings in Palo Alto.

        Spring/Summer 2017

        The Palo Alto City Council Rail Committee directs Staff to develop a white paper on trench scenarios, which will address constraints to a longer trench while providing a more extensive look at the Charleston-Meadow trench.

        City of Palo Alto sends out Community Questionnaire #1 to capture ideas and feedback from the community about issues/concerns related to grade crossings along the corridor.

        City of Palo Alto hosts a Connecting Palo Alto: Community Workshop #1 to engage the public and receive insight on the current challenges and future goals of the rail program.

        Palo Alto City Council directs staff to move forward with Context Sensitive Solutions Alternatives Analysis.


        Fall/Winter 2016

        Measure B is approved by Santa Clara County voters, which includes $700 million for grade separations along the Caltrain Corridor in Santa Clara County.

        Caltrain awards contracts to Balfour Beatty to construct the electrification infrastructure and Stadler to manufacture high-performance electric trains. The electric trains are anticipated to be in service in 2022.

      • 2008 - 2015

        Fall 2015

        As part of a study session, the Palo Alto City Council reviews Palo Alto Grade Separation and Trenching Study and discusses the report findings.


        Fall 2013

        City Council authorizes Hatch Mott McDonald to proceed with an analysis delivering a conceptual cost estimate for a range of preliminary grade separation alternatives south of the California Avenue Caltrain Station. This work would become the 2014 Palo Alto Grade Separation and Trenching Study.

        Spring 2013

        Agreement signed between the California High Speed Rail Authority and Caltrain.

        Winter 2013

        State, regional, and local agencies establish a regional funding memorandum of understanding to support the blended system, which was further defined as “remaining substantially within the existing Caltrain right-of-way and will accommodate future high speed rail and modernized Caltrain service along the Peninsula corridor by primarily utilizing the existing track configuration on the Peninsula.

        Palo Alto Rail Corridor Study approved by Palo Alto City Council.


        Summer 2012

        State Legislature passes Senate Bill SB1029, providing high speed rail funding for construction of the “blended system” as defined in the Revised 2012 Business Plan.

        Spring 2012

        The Peninsula Corridor Joint Powers Board (Caltrain) approves the Peninsula Corridor Electrification Project.

        California High Speed Rail releases the Revised 2012 Business Plan, proposing Silicon Valley to Merced as the initial operations segment for high speed trains, and adopting the blended systems and operations approach for the San Jose-San Francisco segment along the Caltrain corridor. The blended system along the Caltrain corridor was described as “primarily a two-track system that will be shared by Caltrain, high-speed rail service, and current rail tenants.”


        Summer 2011

        California High Speed Rail Authority technical peer review group supports principles identified in the blended system proposal.

        Spring 2011

        U.S. Rep. Anna Eshoo, State Sen. Joe Simitian, and State Assemblyman Rich Gordon officially propose the “blended system” approach for the Caltrain corridor consisting of a primarily two-track system shared between Caltrain and future California High Speed Rail trains.


        Winter 2010

        The Palo Alto Rail Corridor Study is initiated as a component of the city’s response to planned rail investments along the Caltrain rail corridor, specifically the California High Speed Rail project, and potential modifications to Caltrain operations.

        Summer 2010

        Palo Alto City Council authorizes appointment of a 17-member task force to generate a community vision for land use, transportation, and urban design opportunities along the Caltrain corridor, particularly in response to improvements to fixed rail services along the tracks through Palo Alto.


        Winter 2009

        The California High Speed Rail Authority begins the scoping process as part of the project- level environmental review for the San Jose-San Francisco project section. The number of tracks, vertical alignment, and horizontal alignment, among other factors were major issues raised by the City of Palo Alto and other communities along the project section.


        Winter 2008

        California voters pass Proposition 1A, the Safe, Reliable High-Speed Passenger Train Bond Act for the 21st Century, authorizing issuance of $9.95 billion of general obligation bonds to partially fund a statewide high-speed rail system.

      Looking for more historic resources, documents, meeting agendas, and minutes: Visit this archive website.

      Explore FAQ's Here