Crossbore Phase IV-A
Project Description
The Crossbore Phase IV-A Project will inspect 951 private and public sewer laterals throughout the City to verify natural gas pipelines were not installed within the sanitary sewer lateral service. When a natural gas pipeline is unintentionally installed within the sewer lateral, it is known as a Crossbore and must be repaired immediately.
This Crossbore inspection project will be conducted by the City’s Water-Gas-Wastewater Utilities Operations staff. City crews will perform a camera inspection of the private and public sewer lateral to complete the inspection.
Notification letters will be sent to residents prior to the inspection. On inspection days, City crews will inform available residents on-site about the inspection at their property. Residents are not required to be on-site for the inspection.
Access to the front yard, backyard, and side yard will be needed to locate sewer cleanouts. If locked yard access is required, the City will contact the resident to gain access.
The 951 sewer lateral inspections are divided into 4 quadrant areas within the City.
- Quadrant 1 includes 70 sewer inspections on the South side of Alma Street between Sand Hill Road (including Clark Way) and Page Mill Road. Inspected and cleared 51 sewer laterals. The remaining 16 laterals will be scheduled for reinspection.
- Quadrant 2 includes 106 sewer inspections on the North side of Alma Street between Palo Alto Avenue and Oregon Expressway. Inspected and cleared 106 sewer laterals. The remaining 195 laterals will be scheduled for reinspection.
- Quadrant 3 includes 391 sewer inspections on the North side of Alma Street between Oregon Expressway and San Antonio Road. Inspected and cleared 126 sewer laterals. 75 laterals are ongoing for inspection, and the remaining 191 laterals will be scheduled for reinspection, as of March 9, 2026.
- Quadrant 4 includes 204 sewer inspections on the South side of Alma Street between Page Mill Road and San Antonio Road. Inspected and cleared 110 sewer laterals. The remaining 94 laterals will be scheduled for reinspection.
Construction Schedule
The project began in September 2024. Inspections have been completed, but additional reinspection is required for sewer laterals not cleared in Quadrants 1, 2, and 4. Inspections are continuing for Quadrant 3.
Inspection hours are 8 a.m. to 3:30 p.m., Monday through Friday.
Additional work may be needed for laterals that require further inspection.