Capital Improvement Projects

The Regional Water Quality Control Plant is investing $397.2 million dollars in capital improvement projects for upgrades to aging equipment, infrastructure rehabilitation, and new treatment process technologies. A leader in the Bay Area, it is one of the first regional plants to advance these large-scale projects – all while maintaining daily operations to treat 20 million gallons of sewage per day. A Long Range Facility Plan was completed in 2012 that identified these projects as priorities.

The updated facility will increase efficiency and reliability, improve customer service, and prepare for the future. It will proactively comply with new regulations for protecting the San Francisco Bay. The improvements also help the Plant achieve its sustainability goals, such as the reduction of its carbon footprint and improved quality of recycled water.

Environmental Sustainability

Planning for Sea Level Rise in the Capital Projects

Sea Level Rise.jpeg The Plant is a critical infrastructure facility located directly on the San Francisco Bay shoreline. This makes it vulnerable to sea level rise. The designs of current capital improvement projects have planned for future sea level rise. For example: 

  • The Outfall Line Construction will address the discharge capacity to meet peak wet-weather flow, peak high tides and future sea level rise scenarios.  
  • The 12 kV Loop Electrical Upgrades raised electrical equipment above ground level to anticipate increased flooding. 
  • The Horizontal Levee Project pilots a nature-based solution to flood protection and sea level rise. As a pilot, it will answer questions that will inform future levee projects throughout the Bay Area.  

Sea Level Rise Planning in Palo Alto

Horizontal Levee Pilot Project, Fall 2025

IMG_2228-Large.jpeg Located just outside the Plant in the Baylands, the Horizontal Levee will pilot a new type of levee to protect against floods and predicted sea level rise. It will be the first of its kind on the San Francisco Bay and will inform planning for future levees.

A horizontal levee is a nature-based solution that provides many benefits over traditional levees. Their unique designs have a wide gentle slope which helps a marsh adapt as sea level rises. This one will also use treated wastewater to restore a native habitat on its slope. The process will further filter treated wastewater.

Palo Alto Horizontal Levee Pilot Project

Incinerator Decommissioning, 2019

Belt filter press and sludge conveyor_lo res.jpg The Plant decommissioned its sewage sludge incinerators in 2019. The incinerators had been in use since 1972, and their decommissioning was part of an effort to reduce greenhouse gas emissions. The incinerators were replaced by a sludge dewatering and loadout facility (photo on right), which treats and dehydrates solids. The dewatered solids are then transported off-site for further processing. 

Using sludge dewatering instead of incineration to process biosolids reduced greenhouse gas emissions by 15,000 metric tons of carbon dioxide equivalents per year and eliminated the generation of 700 tons of hazardous waste incinerator ash per year.

Ultraviolet Disinfection, 2010

Ultraviolet Disinfection Process The Plant replaced chlorine with ultraviolet (UV) light to disinfect treated wastewater that is discharged to the San Francisco Bay. The UV facility was built in 2010 (photo at left). Chlorine created harmful byproducts and is toxic to aquatic organisms. UV disinfection is both effective in destroying bacteria and viruses in the water and safe for the environment. Chlorine is still used in the production of the Plant’s recycled water.

 

Recycled Water, 2007

The Plant’s recycled water program began in 2007 and generates approximately one million gallons of high quality recycled water each day. This water can be used for landscaping and industrial applications.

Learn more about recycled water

Emily Renzel Wetlands and Pond, 1992

Bird sitting in water with baby birds on its back Most of the Plant’s treated wastewater is discharged into the Palo Alto Baylands, but approximately one million gallons each day is also released to a constructed pond in Renzel Wetlands. It takes the water about 12 days to pass through the pond before entering Matadero Creek, where it travels into the Bay.

 The pond east of the Bayshore Freeway was built in 1992. This project was a requirement of the Regional Water Quality Control Board, which regulates the Plant. The pond and wetlands connection provides a beneficial reuse for treated wastewater effluent. In 2018, the pond was drained and excavated to remove built up sediments, and a perimeter berm and trail was constructed.

Today the pond is an amazing viewing area for wildlife, like migratory birds.